From Back-to-School to Christmas: A Realistic Geneva Renovation Timeline
Updated: 2 days ago

We've been back from summer break for a few weeks now, the kids are back at school, we're back at the office, and we're slowly settling back into our daily routines. Except there's a snag: all of a sudden you notice everything that's wrong with your home. And it's pretty classic. Everything that stopped working for you by the end of spring, but that you put off because "we'll deal with it later" or "let's just enjoy the holidays", suddenly can't wait anymore. We've been out of our routine long enough over the summer that now everything impractical starts to grate on us. And on top of that, you want to break the bad habits and start the new school year off on the right foot.
The problem is that in just over three months, we're hosting family for Christmas. But hey, it'll be fine, it's just a bathroom/kitchen/entryway/[insert your room] that needs a rethink. And when you send me a message along those lines, I usually end up playing the bad guy... Because unfortunately, most of these requests simply aren't realistic in that short a timeframe in Geneva. So before you think I'm just saying no for the sake of it, let me walk you through what's actually possible between September and December, and what isn't.
Why September to December isn't enough time
A renovation project, even a modest one, is really the sum of several phases, and each one has its own conception time and its own round of decisions on your end. Let me walk you through it:

If you want to be guided through it
If you want to hire someone to help you make the best decisions, a few weeks can already go by between the moment you first message me and the moment I actually start the conception phase. Why? Because we'll probably exchange a few emails, then set up a call, then an initial consultation (that's when I come to your apartment or house for the first time), then I send you the quote. You might take some time to look it over, maybe have a few questions about my terms and conditions (always read before signing), and then once it's signed, we need to find a 2-2.5 hour slot together to talk it through, plus another 2-2.5 hours at your place where I take measurements. So all in all, on average, 2 to 3, sometimes even 4 weeks have already gone by.
Consultation, layout and design decisions
Let's say, hypothetically, that I start drawing your floorplans (phase 1) in mid-October. This stage, where I lay the groundwork for the whole project, is very technical, and I provide three different plans based on your needs and the architectural constraints of your existing space. I then meet you again to present the plans around three weeks later. So we're already into early November, and I give you two weeks to think over which one you like best and come back to me if you need a fourth and final plan.
Then comes phase 2 - the style and design decisions - which also takes about three weeks on average. Choosing materials, colours, furniture, and hand-drawn perspective sketches of your interiors. When I present you with the first draft of phase 2, I again give you up to two weeks to share your feedback. At that point, we can go visit showrooms together if you're interested, or I'll do it on my own and finalise phase 2.
Furniture orders and building permits in Geneva

Alongside phase 2, if you've also signed up for phase 3 - building site supervision - with me, that's also when I handle the building permit applications with an architect. In the canton and city of Geneva, unless you have a fully independent villa, you need a permit for... pretty much everything. Partition walls (even non-load-bearing ones), a kitchen, a bathroom, and so on. And that, understandably, takes time. Count on 1 to 2 weeks to brief and file the application, then 1 to 2 months for it to be processed. And if there's back-and-forth involved, it can stretch to as much as 3 months.
And if your apartment sits in the heart of Geneva's Old Town, inside one of the city's protected historic buildings, expect an extra layer of review before the standard permit process even starts. Once the permit is approved, it has to be posted on your front door for a month before you're allowed to start demolition.
Meanwhile, phase 2 keeps moving and we place the orders for furniture and materials for your property, which can take 8 to 12 weeks.
And then there's the site work itself. Once the permits are in hand and the materials have been delivered, what's left is the actual construction: demolition, plumbing, electrical, finishes, coordinating and management of tradespeople. Depending on the scope, expect anywhere from a few days for a light refresh to several months for a full renovation or heritage restoration.
Apartment or house: timelines that don't compare
For a standalone house, you're less subject to permit requirements, so there's less delay when it's purely about interior architecture. Strip the administrative applications out of the calendar and you typically gain 1 to 3 months.
So, what's realistic by Christmas?
Yes, the answer depends entirely on the nature of the project, but once you add up the phases, the timeline quickly becomes clear.
Work with or without a permit: the basics to understand, and what it means for the scope of services
Purely cosmetic renovation - paint, flooring, furniture, lighting - doesn't require a permit and can start as soon as the conception and designs are approved. What can be done: a refreshed living room, a redesigned bedroom, new furniture and paint for a room that's already structurally sound. Without a permit, without any heavy construction, these can absolutely wrap up before Christmas, provided you're quick with your decisions so materials can be ordered and tradespeople secured in time.
What isn't achievable: a kitchen remodel, moving partition walls, a redesigned bathroom, relocating water fixtures, reworking the electrical layout - basically anything that requires a permit. Even starting today, legal requirements and furniture lead times simply don't leave room for a complete overhaul before the holidays.
Choosing the right team: the role of building professionals for quality results
The site work and its supervision follow a precise schedule too - though a potentially shifting one. The real recipe is reliable tradespeople with precise know-how, rigorous site supervision, and materials ordered at the right time. That said, demolition often comes with surprises, which can mean extra days added on. That's why it matters to carefully compare services and quotes, and to choose your team well, so you're able to find solutions quickly and efficiently - which is what makes it possible to reach a result that holds up to the promised quality, within a reasonable timeframe.
Why I'd rather tell you now, and every solutions we can find
I could let you believe that everything is possible in three months. But a poorly planned renovation, with an unrealistic timeline, often leads to rushed decisions, compromises on quality, and major frustrations that could easily be avoided. I'd rather we start on honest grounds than disappoint you along the way and lose your trust. I've built a precise working structure that guides us step by step and prevents exactly this kind of letdown.

If your project fits within the window - a living room, a bedroom, a space to optimise without touching the structure - the start of the school year is a good time to get going to be ready by the winter holidays. If your renovation involves walls, a kitchen, or a bathroom, it's not necessarily out of reach either: we can absolutely kick off the design phases now, so that the demolition can start at the right moment, perhaps right after christmas.
Either way, it all starts with the same first step: a consultation where we look at your space, your needs, and your lifestyle together. That's phase 1 of my services, the one that lays the groundwork before any design decision or site construction. Let's talk about it, and build a schedule, and a home that actually keeps its promises.
XoXo,
FAQ: your questions about the timeline of a renovation in Geneva
How long does it take for full renovation Geneva support, from first contact to the end of the project?
It depends entirely on the scope of yours needs. For a refresh with no permit needed, count on 2 to 3 months between the consultation and the end of the building phase. For renovation Geneva support that includes a building permit, plan for more like 3 to 5 months before the demolition even start.
Can demolition begin before the building permit is granted?
No. Starting before the end of the legal public notice period and before approval is obtained puts you at risk of a stop-order, or even having to restore the site to its original design at your own expense. It's better to keep moving forward with the design and selection phases in the meantime, so you don't lose time once the green light comes through.
Is it possible to renovate a kitchen or bathroom before Christmas, given we're in September?
If you live in a standalone house, yes. In an apartment, probably not. You can swap appliances, change the type of lighting, or make other light updates, but as soon as you touch the structure - even just the fitted furniture - you'll need a building permit, which means a longer process.
Can custom furniture speed up the timeline?
Quite the opposite - custom furniture generally comes with longer lead times than in-stock pieces. If time is tight, prioritising pieces that are readily available is the better option.